WASHINGTON — As the partial shutdown of the federal government over border wall funding stretches past 20 days, some state departments of transportation are beginning to curtail planning for new projects while several mass transit systems are scrambling as many rely on federal grants for both operating revenues and capital funding.
In his first media briefing as the new executive director of the American Association of State Highway and Transportation Officials (AASHTO), Jim Tymon said that since the 115th Congress did not pass FY 2019 appropriations for seven of the 12 annual spending bills, including the Transportation, Housing and Urban Development (THUD) package, states to date are limited to only about a quarter of the federal funding they are scheduled to receive this year, Tymon said
However, in an article published in the Journal of the American Association of State Highway and Transportation Officials, Tymon stressed that the U.S. Department of Transportation employees paid out of the Highway Trust Fund – including all Federal Highway Administration employees – are reporting to duty with pay as usual and that FHWA is able to continue reimbursing states for projects approved prior to the shutdown.
“I think what you’ll see in the short term is states finding ways to move money around from different pots in order to keep their systems operating as efficiently as possible. It’s not something they can do forever,” Tymon said. “The longer this drags on, you’re going to see states start to draw back on their letting for new projects because they won’t have their full allocation of federal money for 2019 yet.”
For example, while a January 8 FHWA funding notice makes $30 billion worth of FY 2019 transportation funding available to be committed by states as authorized under the five-year Fixing America’s Surface Transportation (FAST) Act, the agency also said that it would be “inadvisable” for states to commit a large amount of new federal dollars provided under today’s notice.
For example, if there is a new continuing resolution from Congress lasting just 30 days, any dollars obligated beyond that prorated amount (i.e., 30/365th of full year funding) would then have to be de-obligated or returned to FHWA.
Tymon said that the effect of the FHWA notice is that even if full FY 2019 highway dollars are now technically available, for all practical purposes, states can’t really commit all of those dollars because there’s a real risk of having to return some of them if the shutdown ends with another continuing resolution.
Another worry among state DOTs is how a prolonged federal shutdown could impact the spring/summer construction season.
Oklahoma DOT Executive Director Mike Patterson said in a presentation before the Oklahoma Transportation Commission on January 7 that roughly 45 upcoming highway, county road, and city street projects set to go out for bid in January and February totaling more than $137 million had to be delayed due to the lack of federal funding authorization.
“While we’re very grateful that the Highway Trust Fund remains available to pay for the federal share of projects already under construction, the inability to award new contracts with federal funds could delay some projects from starting for several months.” Patterson said. “If this budget impasse continues, contractors could miss out on some of this year’s prime construction season in the spring and summer.”
The Trucker News Staff produces engaging content for not only TheTrucker.com, but also The Trucker Newspaper, which has been serving the trucking industry for more than 30 years. With a focus on drivers, the Trucker News Staff aims to provide relevant, objective content pertaining to the trucking segment of the transportation industry. The Trucker News Staff is based in Little Rock, Arkansas.